Canyon Falls Retail

Posted on: April 26th, 2018 by Drake Construction

Scope of Work: Staking & Layout, Strip Topsoil, Building Pad – Over-excavate, fill with Select Fill (min 48″) with 5′ Overbuild, Storm drainage, Sanitary service lead, domestic water and fire water service lead, Fine grade Paving Sub-grade, Stabilize with Lime/Flyash, rough grade Sidewalks and Misc. Flatwork, Backfill all Greenbelt areas after concrete is poured.

Address: 9571 West FM 1097, WIllis, TX 77318

General Contractor: Guy Hopkins Construction  guyhopkins.com

Started: 4/26/18

Work Duration: 2 Months