Scope of Work: Job Size – 2.54 Acres, Staking & Layout, Stripping of Topsoil, Saw Cut & Remove 675′ – Curb & Gutter, Excavate an average 1.95′ in proposed parking lot area(88,650 SF), furnish and install storm sewer(30’ – 30” HDPE, 210′ – 15″ HDPE, 4 – Type C Manholes)Proof Roll, Stabilization of Paving Sub-grade with Lime Slurry, 735′ – Curb & Gutter, 14 – Light Pole Bases, 8″ Crushed Stone Base, Asphalt Topping & Sealcoat, Excavate and Grade Retention Basin(20,095 SF), Backfill in all Greenbelt areas, Haul off all excess dirt.
Address: 13100 Gulf Freeway, Houston, TX 77034
General Contractor: Teal Construction http://tealcon.com
Date Started: 8/26/2013
Work Duration: 3 Months