Knapp Chevrolet Showroom and Parking Addition

Posted on: April 17th, 2014 by Chris Drake Construction

Scope of Work: Building Pad: 7,130 sq. ft., Excavate, Haul in and Install Select Fill Material (Min. 36 in minimum thickness w/ 5 ft. overbuild), Concrete Paving Areas: 52,505 sq. ft., Remove old piers and concrete rubble from subgrade, Stabilization of Paving Sub-grade with Lime Slurry,  Grade sidewalks and greenbelt areas

Address: 815 Houston Ave, Houston, TX 77007
General Contractor: TEAL Construction, http://tealcon.com
Date Started: 4/17/2014
Construction Timeline:  10 Months, 4 Phases

 